Vines v. Orchard Hill

181 Conn. 501, 435 A.2d 1022 (Conn. 1980)

  • Mr. and Mrs. Vines contract to buy a condo in Orchard Hill.  They paid a $7880 deposit (10%).  They did not buy the condo because Mr. Vines was transferred to New Jersey.  A clause in the contract said that the deposit was forfeit if the sale did not go through (a liquidated damages clause).  Vines sued for their deposit back.
  • Vines argued that, due to an increasing housing market, the house was now worth $80k more to Orchard Hill since the Vines contract fell through.  They argued that the 10% estimate was not well thought out or reasonable.
  • Orchard Hill demurred.  A demure means that they agree that everything the plaintiff said is true.  However, even though everything they said was true, we should still win.  They did not argue facts, only the law.
  • Trial Court ruled that Orchard Hill had to give back the deposit, irregardless of the clause in the contract.
  • Appellate Court overturned the decision and remanded it back to the Trial Court.
    • Appellate Court found that there was no loss to the non-breaching party.  Based on benefit of the bargain, there is really nothing to recover.  To not give the money back is to punish the Vines.  The Vines partially performed, which should theoretically count more than someone who doesn't perform at all.
      • The Vines are in a worse off place that someone who completely breached and never made the down payment.  Should partial performance be punished more than complete non-performance?
      • Appellate Court found that this is really an efficient breach.  Both parties are better off that the contract failed, so what's the problem?
      • If the damages were known and $0, then why should a liquidated damages clause be in effect?
    • However, Appellate Court believed that Vines' argument that the price had gone up was not valid, because the time to measure the seller's damages is at the time of the breach, not the time after the breach occurred.
    • Appellate Court found that if Vines was not happy with Orchard Hills claims that the deposit was equal to their damages, it is Vines' responsibility to suggest what Orchard Hills' actual loss was and compensate for that.  Orchard Hill did sustain some loss do to Vines' breach, and they are entitled to recover for that amount.
  • One big question with this case is whether the breaching party (Vines) can sue for recovery for a contract they breached!