Cochran
contracted to send 36k tons of coke to Missouri Furnace at $1.20 a ton, 2k
tons per month.Cochran only
delivered ~4 tons and cancelled the contract.
In
response, Missouri Furnace made a long-term contract with another company
to deliver the remaining 29k tons of coke at $4 a ton over the course of
the rest of the year.
That
was the market rate (aka spot price) at that specific time, but was
considerably higher than the typical market rate.
Missouri
Furnace sued Cochrane to recover the difference ($4.00-$1.20 = $2.80 per
ton).
The
Trial Court ruled that the recovery should be "the difference between
the contract price (what Cochran was the receive) and the market price of
standard coke at the price of delivery, at the several dates when the
deliveries should have been made under the contract."Missouri Furnace appealed.
This
meant that they figured out what the spot price of coke was every day for
the rest of the year and worked out the difference between the spot price
that day and the contract price.
The
Court found that Missouri Furnace did
act in good faith in making the $4 a ton contract, even if it wasn't a
good deal in the long term.There was no attempt to run up damages.But, in the view of the Court, Missouri Furnace is
stuck with the risk of price fluctuations.
The
Appellate Court affirmed, saying:
The
measure of damages is the difference between the contract price and the
market value of the article at the time is should be delivered.This means that the "time of
the breach" is technically the "time when delivery should have
been made".Where
delivery is required to be in installments, the measure of damages shall
be estimated by the value at the time each delivery should have been
made.
The
issue here is whether Missouri Furnace should have signed a long term
contract at that high rate, or realized that the rate was probably going
to drop and therefore should have signed only a short term deal and
bought more later, when the price had dropped.The 2nd contract was at Missouri Furnace's
own risk and damages cannot be blamed on the 1st contract.
This
Court case was poorly decided, because if the spot price had gone higher than $4 a ton, the Court would
have not awarded the spot-contract price, it would most likely have capped
damages at $2.80 per ton.In
this case, the court has put the entire risk on the plaintiff!
This
case was decided prior to the UCC,
so it would never be cited in a new case.
UCC
§ 2-712 repudiates the decision of Missouri
Furnace v. Cochran.In the UCC, all the Missouri
Furnace would have been required to do while covering is make a commercially
reasonable purchase, which they did.As long as the purchases are made in good faith, then the defendant is liable for the
difference between the cover price and the contract price.
This
commercially reasonable standard
doesn't fly in other legal situations.For example, if you get caught speeding, you can't use
the argument that speeding is the way most people drive.